Dilip Buildcon has received completion certificate for Wardha-Butibori section in Maharashtra.
The scope of work envisages four-laning of Wardha-Butibori Section of NH-361 from 465.500 km to 524.690 km (design length 59.190 km) under NH (O) in the state of Maharashtra on hybrid annuity mode.
The appointed date for the project is 30 November 2017 and completion period was 910 days from the appointed date.
The project cost is Rs 1,065.51 crore.
The completion date is 4 January 2022.