The National Highways Authority of India (NHAI) has issued Dilip Buildcon a letter of the completion certificate for the four-lane highway project NH-166 on hybrid annuity mode (HAM).
The project is valued at Rs 1102.40 crore. The project entails four-laning of Sangli-Solapur (under package-1, from Sangli to Borgaon) section of NH-166 in Maharashtra, extending from existing Ch. km 182.195 to Ch. km 219.956 (design Ch km 182.556 to km 224.000).
The contract was awarded to Dilip Buildcon on 23 May 2019, with a completion date of 730 days.
The project was completed on 18 February 2023.