Illustrative image – not actual.
Road construction company, Dilip Buildcon (DBL) has received the Letter of Award (LoA) for three road projects on a single stretch of NH-361 in Maharashtra, from National Highways Authority of India (NHAI). The projects are to be executed under hybrid annuity mode. These include:
1. Four laning of Mahagaon - Yavatmal section having a total length of 80.195 km from 320.580 km to 400.575 km (Package-II), under NHDP Phase-IV, at a project cost of Rs 1,160.64 crore.
2. Four laning of Yavatmal - Wardha section having a total length of 64.925km from 400.575 km to 465.500 km (Package-III), under NHDP Phase-IV, at a project cost of Rs 1,043.28 crore.
3. Four laning of Wardha - Butibori section from 465.500 km to 524.690 km (design length 59.190 km) under NH (O), at a project cost of Rs 1,065.51 crore.
The completion period for all the above projects is 30 months.