Dilip Builcon receives provisional certificate for Gorhar to Khairtunda sectionIllustrative image – not actual.
Dilip Buildcon (DBL) has received provisional certificate from the National Highways Authority of India (NHAI) for Gorhar to Kahirtunda section in Jharkhand.

The provisional completion certificate was issued for 16 October 2021.

The scope of work envisages six laning of Gorhar to Kahirtunda section of NH-2 from 320.8 km to 360.300 km in the state of Jharkhand under NHDP Phase-V on hybrid annuity mode (HAM). The project cost is Rs 917 crore and scheduled completion date was 18 July 2021.