Diamond Power commissions Phase-I of expansion project     Illustrative image – not actual.

Diamond Power Infrastructure has commissioned Phase-I of cable and conductors' facilities, located at Phase-II, Vadadala village in Vadodara district of Gujarat.

 

The estimated cost of the project is Rs 753 crore. With the commissioning of Phase-I, the project will add 3,000 km of MV cables and 50,000 tpa of conductors.

 

Phase-I of the cable and conductors' plant will commence commercial production on 1 February, 2014.

 

The project will have a capacity to produce additionally 7,500 km of MV cables and 2,00,000 tpa of conductors, and a backward integration to product /  compounds  / polymers and steel wires required for both, cables and conductors, which is expected to be fully commissioned in June 2014 in three phases.

 

Related Link:
Project profile

← All latest storiesBack to top →