Dholera water treatment plant by 2019Illustrative image – not actual.
The Dholera Industrial City Development (DICDL) has undertaken implementation of a water treatment plant at TP2E in DSIR, Dholera in Ahmedabad district of Gujarat. The facility will have a treatment capacity of 50 mld.

The work order secured by SPML Infra in late 2016, included scope of work like construction of a water treatment plant, clear water reservoir, master balancing reservoir and pumping stations and entails the operation and maintenance at the facility. As per the contract document, the construction cost of the plant would be Rs 94.85 crore.

The work on the project started in May 2018, nearly after two years of awarding the contract. During a recent visit to project site, the representative of Projects Today uncovered that around 10 percent work on the project has been accomplished so far. The construction work is scheduled for completion in March 2019.

← All latest storiesBack to top →