Illustrative image – not actual.National Hydro-electric Power Corporation (NHPC) will begin generation from its 280 MW Dhauli Ganga power project in Uttaranchal in March 2005.
The first unit of the 4x70 MW plant on the River Dhauli Ganga will be functional in March 2005 and the other three units by August-September 2005.
The hydel project will generate 1,134 million units of electricity ,which will be evacuated by a transmission line of Power Grid Corporation for supplying to the northern grid. The states which will get benefited are Uttaranchal, Delhi, Haryana, Punjab, Himachal Pradesh, Rajasthan, Uttar Pradesh and Jammu & Kashmir.
The project estimated to cost Rs.1,578 crore, is being funded by Japanese Bank of International Cooperation to the extent of over Rs.924 crore.
For detailed project profile, click here.