DGH to grant extension to upstream majorsIllustrative image – not actual.

Director General Hydrocarbons, the upstream regulator, had recommended extension of deadline for companies to drill exploratory wells in block awarded in NELP-III and VI rounds by at least two years because a shortage of rigs was delaying drilling plans.

It is proposed that 3-year exploration phase-I may be extended to 5 years by including two years of Phase-II. Phase-II and III development and production phases may be combined.

Currently, oil firms win oil blocks based on their commitment to drill - 3 years for exploratory drilling and 2-3 years for developmental and production drilling.

DGH had proposed extending deadline for Phase-I for 43 blocks awarded in NELP-III and IV rounds, most of which went to Reliance Industries and ONGC. Both these companies had asked for an extension due to lack of available rigs.

The government had awarded 23 blocks in NELP-III and 20 blocks in NELP-VI round.