DGH extends deadline to drill exploratory wellsIllustrative image – not actual.

Directorate General of Hydrocarbons plans to extend the deadline for oil firms to drill exploratory wells in blocks awarded in previous NELP rounds by two years, due to shortage of drilling rigs.

 Empowered Committee of Secretaries (ECS)  agreed with the proposal of DGH to extend exploration phase by two years in 25 offshore blocks awarded in third and fourth round of auction under New Exploration Licensing Policy (NELP). DGH had recommended for extension after consultant Rig Management Norway AS indicated that none of the drilling rigs for deep water exploration were available before March 2009.

ECS has reclassified the earlier three phase exploration programme (three year Phase-I, two year Phase-II and two year Phase-III in case of shallow water blocks and four year Phase-I, two year Phase-II and two year Phase-III in case of deepsea blocks) into just two.

The new Phase-I exploration period, where companies are mostly required to do seismic survey and drilling only a handful of wells, will be of five years by merging timeframe of old Phase-I and Phase-II. The New Phase-II will now include the minimum work programme (wells committed) of old Phase-II and Phase-III.

The scheme will be optional and contractors who avail of this dispensation will be required to relinquish 50 per cent of the area at the end of new exploration Phase-I. The ECS recommendation will now go to the Cabinet Committee on Economic Affairs (CCEA) for approval.

Explorers have drilled less than half of the 218 wells committed under exploration blocks awarded by the Government since 2000. In order to ensure completion of MWP in the new Phase-I by the contractors, a 100 per cent bank guarantee of the unfinished MWP will be sought for those who exercise to take up such an option.