The last blast of the escape tube of under-construction Sela Tunnel was conducted by Director General Border Roads (DGBR) Lt Gen Rajeev Chaudhry through video conferencing on 22 July 2021.
This breakthrough will facilitate faster completion of Sela Tunnel by undertaking simultaneous activities in two tubes i.e., a two-way tube of 1,555 mtr and an escape tube of 980 mtr, besides 8.8 km of approach roads.
DGBR had initiated the first blast of the escape tube in January 2021. This tube has already crossed the 425 mtr excavation mark.
Prime Minister Narendra Modi had laid the foundation stone of Sela Tunnel on 9 February 2019 to provide all-weather connectivity to Tawang, Arunachal Pradesh, through the Balipara-Charduar-Tawang Road.
The construction of the tunnel started on 1 April 2019 with the first blast taking place on 31 October 2019.
The excavation pace of Sela Tunnel has been swift as it has resulted in the breaking down of the escape tube of the 1,555 mtr tunnel on 22 July 2021, much ahead of schedule.
Despite COVID-19 restrictions and adverse weather conditions, the pace of works has increased in the last six to10 months. On completion, Sela Tunnel will be the longest bi-lane road tunnel in the world at an altitude above 13,000 ft.
This unique tunnel constructed using the latest New Austrian Tunneling Method (NATM), is much below the snow line allowing all weather travel without the challenges of snow clearance.
The Sela Tunnel will prove to be a boon for the people of Tawang as it will reduce travel time and ensure speedier movement across the Sela Pass.
It will play a crucial role in the development of not just Arunachal Pradesh, but the entire North-East. In case of natural calamities and adverse weather, it can prove to be a vital link for evacuation of personnel.