Dedicated Freight Corridor Corporation of India (DFCCIL), the Indian Railways' arm implementing the ambitious freight corridor project, will award contracts worth Rs 14,000 crore in the current financial year, 2016-17, in a bid to quickly wrap up work and meet the 2019 deadline for commissioning the Rs 82,000 crore project.
By July 2016, orders worth Rs 10,000 crore will be placed. The balance, around Rs 4,000 crore worth of contracts, will be placed later in the current financial year.
The company has so far placed 76 percent of the contracts for civil works and 63 percent of electrical contracts, apart from 48 percent of the total signalling contracts.
For the construction of the Eastern Dedicated Freight Corridor, contracts worth Rs 4,000 crore were awarded in 2013, followed by another Rs 5,000 crore contracts in 2014. Last year, the DFCC placed around five contracts for signalling and telecommunication, electrification and civil construction. Similarly, nine contracts were placed for Western Dedicated Freight Corridor.
The Eastern DFC accounts for around 40 per cent of the total project cost. Phase-I of the project between Khurja and Mughalsarai is being funded through 66 percent debt from World Bank and the rest as equity from the rail ministry.
Phase-II corridor between Mughalsarai and Sonnagar is being funded entirely through government equity, while the third phase between Sonnagar and Dankuni is to be developed on public-private partnership (PPP) mode.
The DFCC is constructing the 3,350 km long freight corridor project, including the 1,800 km of its eastern arm between Ludhiana and Dankuni, in West Bengal. The Western DFC will come up between Dadri in Uttar Pradesh to Jawaharlal Nehru Port in Mumbai.
The project, when commissioned, will take up more than 70 percent of Indian Railways freight traffic onto its faster, longer and heavier trains.