Illustrative image – not actual.A Deutsche Bank-led consortium that had won a bid to buy out the debt of Jindal India Thermal Power (JITPL) has placed the acquisition on hold due to COVID-19 pandemic.
The consortium had been the sole bidder for the asset, and thus a resolution may be a long time in coming.
JITPL is a 1,200 MW coal-fired power plant in Odisha’s Angul district, owned by the Jindal Group. It owes nearly Rs 7,600 crore to a clutch of 17 lenders, led by the Punjab National Bank.
The lenders hold 51 percent in the unlisted JITPL after shares pledged by the promoter company were invoked because of difficulties in repaying bank loans. Since 2017, lenders have sought bids to sell their 51 percent stake.
The Deutsche Bank-led consortium had offered Rs 2,400 crore for the asset.
A total of 34 thermal power projects, accounting for 40 GW of generating capacity, have been stalled for either want of long-term power purchase agreements or shortages in availability of coal and natural gas.
The consortium had been the sole bidder for the asset, and thus a resolution may be a long time in coming.
JITPL is a 1,200 MW coal-fired power plant in Odisha’s Angul district, owned by the Jindal Group. It owes nearly Rs 7,600 crore to a clutch of 17 lenders, led by the Punjab National Bank.
The lenders hold 51 percent in the unlisted JITPL after shares pledged by the promoter company were invoked because of difficulties in repaying bank loans. Since 2017, lenders have sought bids to sell their 51 percent stake.
The Deutsche Bank-led consortium had offered Rs 2,400 crore for the asset.
A total of 34 thermal power projects, accounting for 40 GW of generating capacity, have been stalled for either want of long-term power purchase agreements or shortages in availability of coal and natural gas.