The government has set a target for commencement of the Delhi-Surat segment on Delhi-Mumbai Expressway by March, 2024, with two additional stretches of over 300 km nearing completion.
As per a Ministry of Road Transport and Highways (MoRTH) document, a 100 km section between Vadodara and Ankleshwar is nearly completed and is poised for inauguration. Another 205 km stretch between Lalsot and Jhalawar is moving towards completion, with significant progress in various packages along the route. Out of the 1,386 km Delhi-Mumbai Expressway, approx., 67 percent of the work on the 920 km stretch has been achieved so far. The Ministry plans to open sections which are ready, with four packages between Vadodara and Ankleshwar expected to be operational in the coming weeks.
However, two critical sections, a 26 km-long section has witnessed 75 percent completion, while an eight km-long segment has progressed to 45 percent. The Delhi-Mumbai Expressway will traverse Haryana, Rajasthan, Madhya Pradesh, Gujarat, and Maharashtra. With a development cost of around Rs one lakh crore, it is poised to be India's longest expressway, and would reduce the travel time between Delhi and Mumbai from 24 hours to 12 hours and shortening the distance by 130 km.
The project aims to enhance connectivity to key economic hubs and will also bring down CO2 emissions. The entire Delhi-Mumbai section is anticipated to be open for traffic movement by December, 2024 while the Mumbai to Jawaharlal Nehru Port Trust (JNPT) segment is slated for completion in 2025.