Delhi MSW Solutions misses deadline for waste-to-energy plantIllustrative image – not actual.

Delhi Municipal Solid Waste Solutions has missed its deadline for the Narela Bawana waste-to-energy plant.


The 48 MW plant, expected to be commissioned in August 2013, is now expected to be commissioned in December 2013. However, the finance required for the project has been delayed as the bank loan applied for requires time. The loan hasn't been received due to certain necessary documentation which has not yet been done. The plant is to be built with Chinese technology.


The project, being developed in two phases each, with 24 MW capacity, is estimated to cost Rs 500 crore. The unit will recycle 8,000 tonne of garbage generated per day.

 