Delhi MRTS project bogged down by cost overrunsIllustrative image – not actual.

The Delhi Mass Rapid Transport System (MRTS) is facing a cost overrun of around Rs.351 crore. This overrun is a result of paucity of funds, acquisition of land and delays in the awarding of contracts.

 

The cost of the project has risen to Rs.5,211 crore as against the earlier-envisaged Rs.4,860 crore. The project is expected to be completed by March 2005.

 

As per the Ministry of Planning, the project is expected to adhere to the following progress chart.

 

From

To

Distance (km)

Completion

Shahdara

Tees-Hazari

8

March 2002

Tees-Hazari

Tri Nagar

5

June 2003

Tri Nagar

Barwala

15

December 2003

Vishwavidyala

ISBT

4

July 2004

ISBT

Central Secretariat

7

March 2005

Total

 

39

March 2005

 