Illustrative image – not actual.The Delhi Mass
Rapid Transport System (MRTS) is facing a cost overrun of around Rs.351 crore.
This overrun is a result of paucity of funds, acquisition of land and delays in
the awarding of contracts.
The cost of the
project has risen to Rs.5,211 crore as against the earlier-envisaged Rs.4,860
crore. The project is expected to be completed by March 2005.
As per the Ministry
of Planning, the project is expected to adhere to the following progress chart.
|
From |
To |
Distance (km) |
Completion |
|
Shahdara |
Tees-Hazari
|
8 |
March
2002 |
|
Tees-Hazari |
Tri Nagar |
5 |
June
2003 |
|
Tri Nagar |
Barwala |
15 |
December
2003 |
|
Vishwavidyala |
ISBT |
4 |
July
2004 |
|
ISBT |
Central Secretariat |
7 |
March
2005 |
|
Total |
|
39 |
March
2005 |