Delhi Metro Phase-IV work to begin by November-end 2019Illustrative image – not actual.

After a delay of more than three years, construction of Delhi Metro’s Phase-IV project is finally going to start by the end of November 2019. The first civil contract of the Delhi Metro Rail Corporation’s (DMRC) Phase-IV project has been awarded for construction of a portion of the Janakpuri West-R K Ahsram Marg corridor, which is an extension of Magenta Line (Botanical Garden-Janakpuri West).

 

The contract includes construction of a portion of the corridor, with 10 stations -- Keshopur, Paschim Vihar, Peeragarhi, Mangolpuri, West Enclave, Pushpanjali, Deepali Chowk, Madhuban Chowk, Prashant Vihar and North Pitampura. This was also the first Phase IV tender to be floated by DMRC.

The given work involves design and construction of elevated viaduct, elevated ramp, siding line and station buildings. The work on this corridor is expected to commence by the end of November 2019 and scheduled to be completed within 30 months.

The 28.9 km long Janakpuri West-R K Ashram Marg corridor, Phase-IV’s longest, will come up with 22 stations. The Phase-IV project comprises six corridors with a combined length of nearly 104 km. While Delhi government had approved all the six proposed corridors in December last year, three priority corridors -- of 61.6 km -- were approved by the Centre in March 2019, including the Janakpuri West-RK Ashram Marg.

The other two corridors are Aerocity-Tughlakabad (20.2 km) and Majlis Park-Maujpur (12.5 km). At present, Delhi Metro is engaged in the preparatory work for the priority corridors of Phase-IV, under which 46 stations will be constructed. These new sections will provide inter-connectivity among the already operational sections of the Metro.