Illustrative image – not actual.The Union Minister of State for Road Transport and Highways (Independent Charge), Maj. Gen. B C Khanduri (Retd.), reviewed the progress of the work being carried out on the Delhi-Kolkata section of the National Highways Authority of India’s Golden Quadrilateral Project.
The Delhi-Kolkata stretch of Golden Quadrilateral has a total length of 1,453 kms. Out of this, 322 kms comprising the stretches from Delhi to Agra and Barwa Adda to Panagarh (West Bengal) have been 4-laned already. Work is being implemented on a length of 1,047 kms. The balance of 84 kms (Allahabad bypass) is yet to be awarded.
The minister reiterated that the Government has set for itself December 2003 as the target date (pre-poned by a year) for substantial completion of the Golden Quadrilateral, which is a part of the National Highways Development Project. The Government is drawing up a time-bound plan to achieve completion of the project by the revised target date.