Delhi-Kolkata arm of GQ only 82pc completeIllustrative image – not actual.

The Union Ministry of shipping, road transport and highway in a public statement has said that 82 per cent of the Delhi-Kolkata arm of NHAI's Golden Quadrilateral Project was complete as of 31 May 2006. Around 18 per cent (or 261 km) of the total stretch of 1453 km is facing delays on several counts.

The ministry has committed to complete the Delhi-Kolkata arm by end-December 2006, except for 120 km of stretches. In the best case, therefore, the project will achieve only 91.7 per cent completion.

The following is a summary of the affected stretches.

Stretch Reason for delay Affected length
km per cent
Barwa-Adda Land acquisition 14 5.4
Kanpur-Khaga
Handia-Varanasi Contractor delay 56 21.4
Etawah-Rajpur
Allahabad Bypass Work awarded pre-2004 72 27.6
Aurangabad-Barwa Adda Law & order problem 40 15.3
Sasaram-Delhi-on-Sone
Shikohabad-Etawah Terminated/Re-awarded 73 28.0
Etawah Bypass
Vivekananda Bridge Litigation 6 2.3
Total   261 100.0