Illustrative image – not actual.On 22 July 2008, the Delhi government cleared seven energy and infrastructure development projects worth Rs.347 crore ($82.6 million). The projects were cleared in an expenditure finance committee (EFC) meeting. Out of seven, four projects are related to public works department (PWD) and one each to power, land and building, and irrigation and flood control departments. This include
- Rs.126 crore has been sanctioned for supply, erection, testing and commissioning with complete civil works with automation of 400/220/66 kV sub-station at Mundka.It will be executed on turnkey basis within 24 months from the date of award of work.
- Construction of railway over bridge (ROB) and road under bridge (RUB) at railway level crossing near Nand Nagri Delhi, with an estimated cost of Rs.107 crore also got the EFC nod. The project will be executed within 30 months after the award of tender.
- Rs.89 crore for construction of a RUB at railway level crossing number 7 between Shalimar Bagh and Azadpur fruit mandi near Rajasthan Udyog Nagar have also been sanctioned. This project would be completed within 30 months after the award of work.
- Rs.9.7 crore for the widening of the eastern approach road of ISBT Bridge from three lanes to four lanes. The project will be completed within 21 months.
- Construction of 1,300 mtrs service road along with eastern approach road with side drain and footpath on IT Park/DMRC/Shyam Giri Temple side with an estimated cost of Rs.4.7 crore.
- Rs.7.5 crore has been sanctioned for revamping Najafgarh drain from Amberahi bridge to Kakraula bridge.