Illustrative image – not actual.The Delhi government has sought an allocation of 13.5 million cubic metres per day (mcmd) of natural gas from the new gas discoveries for its proposed 700 MW gas-based power plant at I P station and 1,000 MW power project at Bawana.
The state government has reportedly approached the Petroleum Ministry for the 5.5 mcmd of gas requirement for its I P station plant and 8 mcmd of gas need for the Bawana plant.
It may be mentioned that at present, the load met in Delhi is around about 3100 MW, which by 2005, is likely to exceed 4,000 MW. Due to pollution problems and scarcity of land for ash dumping, the option of gas-based power station seems feasible than the coal-based power stations.
In the existing
coal-based power plant at I P Station, as a replacement of unit No. 1, a
gas-based power plant of 700 MW can be installed; and at Bawana a 1,000 MW
gas-based power station can be implemented subject to availability of gas.