Delayed work on Bangalore-Mysore road project to begin by NovemberIllustrative image – not actual.

Nandi Infrastructure Corridor Enterprises (NICE), a new company promoted by Bharat Forge/ Kalyani Group plans to begin the much delayed work on its Bangalore-Mysore Infrastructure Corridor (BMIC) on 01 November 2008.

The implementing agency is now looking at awarding the 10 km work per contractor . The government had decided to release land for the project in three phases of 7,000 acres of land each. The construction of satellite towns along the expressway will begin in the second phase of the project. All the land losers will be given the price fixed by the Government, in addition to a site.

So far, the promoters have completed 39.5 km of the total length of 41 km of peripheral road; 7.1 km of the 9.1 km of link road and only 4.5 km of the expressway to Mysore. The remaining roadblocks include:

  • On Link Road (9.1 km taking off from SH 17 - Kavika and linking the expressway)
  • Between 0 and 0.6 km linking expressway and Mysore Road near Byatarayanapura and Divitigeramanahally village
  • At 1.4 km, BBMP is yet to communicate approval for diversion road at Ring Road and integrating bridge and ramps across Outer Ring Road, which is pending for the past one and a half years
  • Between 2.6 km to 2.9 km near Hosakerehalli
  • At 5.4 km, alignment in BWSSB water pipeline has to be shifted
  • Between 7.80 km and 8.30 km near Hemmigepura village for formation of link road
  • On Peripheral Road (Tumkur Road to Hosur Road connecting Magadi, Mysore, Kanakapura and Bannerghatta roads)
  • Between 8 km and 9 km on Bannerghatta Road junction, near Gottigere village for formation of road, ramps and slip roads to provide entry and exit to peripheral road
  • Between 15.4 km and 16 km near Kanakapura Road junction of Thalaghattapura village land required for ramps and slip road for entry and exit to peripheral road and land near U M Kaval village required to relocate high tension power line to facilitate construction of peripheral road, ramps and slip road
  • Between 23.4 km and 24.2 km near Mysore Road junction, clearance for construction of bridge across Mysore-Bangalore Road and land near Kengeri for construction of ramps/slip road for entry/exit to peripheral road
  • Between 33.6 km and 33.8 km near Magadi Road junction near Hosahally Gollarapalya for construction of ramps/slip road for entry/exit to peripheral road On Expressway (from Bangalore to Mysore)
  • Land required for laying of road from 5 km to 13.2 km is 184 acres of land. And 100 acres of land for formation of two interchanges. They fall in Gangasandra, Chinnakurchi, Vasanthahalli , Gonipura, Thippura, Hampapura, Talakuppe and Bheemanahalli.

The project is expected to be completed by December 2009.