Delayed Shri Sai Priya Sugar unit by 2018Illustrative image – not actual.
In 2011, Shri Sai Priya Sugars initiated to set up a refined sugar unit at Kallapur, Chirlakoppa, Badami taluka in Bagalkot district of Karnataka. However, the progress on the project was at a snail’s pace due to land acquisition issues. Therefore, the project was kept on hold till mid-2016 and the work got commenced only in late 2016.

As per the report filed by a representative of Projects Today as of mid-July 2018, around 90 percent work on the project was completed. Shri Sai Priya Sugar is confident of commencing sugar production by 2018-end.

The sugar unit with a capacity of 9,10,800 tpa is supported by a 30 MW co-generation captive power plant. The project is spread over 200 acre of land.

Consultancy service to the Rs 200 crore project is from its in-house team. S S Engineers is the project supplier and Tejas Construction and Infrastructure is the contractor for the project.