Delayed Punjab/Haryana Border-Jind section pre-scheduledIllustrative image – not actual.
The National Highways Authority of India (NHAI) has taken up upgradation of four-laning of Punjab/Haryana Border-Jind section of NH-71 from 239.695 km to 307.000 km in Jind district of Haryana on EPC basis under NHDP-IV B. The length of the highway project is 70 km.

The project was initiated in year 2010. After a duration of two years by June 2012, the foundation stone was laid by the then Minister of Road Transport and Highways (MoRTH) Dr C P Joshi and Chief Minister of Haryana Bhupinder Singh Hooda.

In 2015, the contract awarded to Unity Infraprojects was terminated due to poor work performance.

The re-tendered project job was awarded to Dineshchandra R Agarwal Infracon in 2017. Soon, work was re-commenced on the highway and as per the Projects Today research team, the highway will be ready by June 2019.

When a representative of Projects Today contacted the promoter recently, it was learnt that around 50 percent work on the highway has been completed. Based on the progress made so far, the promoters are confident of completing the highway by March 2019, i.e. three months ahead of the re-scheduled completion date.