Illustrative image – not actual.The delay has led to a cost escalation in the project from Rs 14,100 crore to an estimated Rs 18,800 crore -- an increase of over Rs 4,600 crore.
The 72 km long metro project with 66 stations which was supposed to be completed by April 2016 will be now be taken up in three phases.
The second phase of the corridor -- barring a six km stretch near Charminar -- of 66 km and 61 stations was expected to be commissioned by November 2018. The second stretch too is behind schedule by 31 months.
The date of the final stretch or third phase, barring six km, is yet to be decided.
The first phase of the project -- of 30 km and 24 stations will be inaugurated by Prime Minister Narendra Modi on 28 November 2017.
L&T has been given extension of time upto November 2018 on account of delay in right of way (RoW).