Illustrative image – not actual.According to reports, the delay in vacating encroachers for the road over bridge at MIT gate near Chennai, Tamil Nadu, is likely to delay the project.
The Rs.22 crore project, which would come up near Chrompet, about 12 kms from Chennai, began in November 2000 and is scheduled for completion in November 2002. However, it is feared that if the required land is not acquired soon then the project would not be completed on schedule.
The bridge measuring 1,661 metres has been designed
to have a six-arm elevated rotary above the GST Road at a height of 6 metres. The
width of the approach roads would be 6.5 metres and that of the service roads would
be 5.5 metres. The rotary would have an inner diameter of 30 metres with an
outer diameter of 47 metres to channelise traffic with ample space below to
accommodate 6 laning of the GST Road.
About 40 per cent of the work has been completed,
including construction of pillars at both ends connecting the East and West
parts of the MIT gate. According to reports, the railway portion of the over
bridge is almost completed, except for minor issues relating to alignment of
traction lines below the bridge portion.