Delay in developing coal mine turns expensive for APMDC   Illustrative image – not actual.

The Ministry of Coal has ordered a deduction of Rs 2.24 crore from the bank guarantee given by Andhra Pradesh Mineral Development Corporation (APMDC) for delaying the development of a coal mine in Madhya Pradesh.

 

Out of the bank guarantee of Rs 5.81 crore given by the APMDC, the Ministry has ordered a deduction of Rs 2.24 crore, for delay in developing the Suliyari block in Madhya Pradesh.

 

Also, the coal ministry has warned the corporation that further delay in developing the block will lead to cancellation of the said block.

 

In 2007, the Suliyari block in Madhya Pradesh was allotted to the Andhra Pradesh Mineral Development Corporation, which has a geological reserve of 141 million tonne.

 

The decision to deduct the bank guarantee was taken based on the recommendations of an Inter-Ministerial Group (IMG), which reviewed the progress made on coal blocks allotted to private and public sector companies for their own use.

 

The panel found that the mining plan approval, environment and forest clearance, previous approval of central government, grant of mining lease, mine opening permission and coal production are pending.

 