Illustrative image – not actual.The NHDP-Phase II project is unlikely to be completed within its deadline of December 2007, according to press reports.
Of the 7,300 km that form part of the project, only 707 km were complete (four-laned) as of 31 March 2005. Further, as of 31 March 2005, only 29 contracts were awarded out of the total 5,616 contract that encompass the entire project.
By current thinking, the project is likely to be completed only by June 2008.
The NHDP-II project, also known as East-West North-South corridor project involves the four-laning of 7,300 km of highways connecting Silchar (East) to Porbunder (West), and Srinagar (North) to Kanyakumari (South). Phase I of the NHDP is the Golden Quadrilateral (GQ) project that aims to connect the four metros -- Mumbai, Delhi, Kolkata and Chennai. This project is on the verge of completion.