Illustrative image – not actual.ONGC's project of expanding the capacity of its Tatipaka mini refinery in Andhra Pradesh is likely to get delayed. According to information available with ProjectsToday, the project is still in the design and engineering stage with physical work expected only by December 2005. The project would have a gestation period of 6-12 months, implying commissioning in the second half of 2006.
The Rs.30 crore project aims to enlarge refining capacity from the existing 66,000 tpa to 2 lakh tpa. The originally envisaged completion date was July 2005.
In June 2004, the company began the basic engineering of the project and expected to start the tendering process shortly thereafter. It is now learnt that the tendering activity is yet to begin.