Illustrative image – not actual.The Defence Ministry has permitted the Cochin Port Trust's plan to install tall cranes (up to 120 metres height) at Vallarpadam as part of the port's scheme to develop a container transhipment terminal on the island. The project, which is to be implemented on a BOT basis, would entail an estimated investment of Rs.2,000 crore.
Earlier, the Ministry had expressed reservations about allowing the port authorities to install tall cranes at Vallarpadam following the objection raised by the Indian Navy, which felt that the proposed terminal, complete with tall cranes and other huge structures, would interfere with its flying zone, where the permissible height was only 45 metres above the mean sea level.
It may be added that five firms have responded so far to the Cochin Port Trust's invitation for Request For Qualification. These firms are CSX World Terminal UK, Maersk A/S Mumbai, NYK Lines Japan, L&T Chennai and PSA, Singapore. The evaluation of the bids is in progress.
Infrastructure Development Finance Company has been appointed the project consultant.
As the proposed project is to be located on an island, land-bridging with Ernakulam and Vypeen on the mainland is needed, for which the port authorities, in partnership with the State government, are working on an elaborate scheme to provide the connectivity.
A scheme has been worked out, according to which about 25 hectares of land will be reclaimed from the backwaters now under the control of the port authorities. The reclaimed land will be sold, and the proceeds used for funding the construction of the bridges.
Further, new
road networks have to be built to ensure smooth flow of containers to and from
the hinterland. These roads have to be such that they avoid the congested city
area and connect the National Highways Number 17 and 47 with NH 49. The
National Highway Authority of India has reportedly commissioned its consultant,
Intercontinental Consultants and Technocrats, to prepare a detailed project
report.
The project also needs to have connectivity by rail. Konkan Railways has completed the survey work in this respect.
For Related News:
Naval team to undertake security aspects study for Vallarpadam terminal project
Vallarpadam container project foundation stone likely to be laid in April 2003