Dilip Buildcon (DBL) has received provisional completion certificate for a road project in the state of Maharashtra.
The project involving four-laning of Mahagaon to Yavatmal section of NH-361 from 320.580 km to 400.575 km (Package-ll) under NHDP Phase-IV on hybrid annuity mode (HAM) has been provisionally completed.
The provisional completion certificate has been issued by the authority and declared the project fit for entry into operation as on 23 May 2020.
The cost of the project is Rs 1,160.64 crore. The appointed date was 28 February 2018 with a completion period of 910 days.
The scheduled completion date for the project was 26 August 2020. However, the company had applied for EOT of 180 days on account of COVlD -19 and the revised schedule completion for the project was 22 February 2021.
The provisional completion date is 23 May 2020 and the company has completed 275 days prior to the revised scheduled completion date.