Daund-Wadi rail project to be executed on fast modeIllustrative image – not actual.

Work on the Daund-Wadi rail project in Maharashtra is to be taken up on fast track mode. The project which comprises doubling rail track and converting it in electric line, has been sanctioned Rs 1,513 crore by the Asian Development Bank.

Of the total amount, Rs 713 crore has been allocated for track-doubling and the rest for electrification. Tenders for the project are to be floated in March 2011 and the work is expected to begin in July 2011. The project is to be completed in three years time.