Illustrative image – not actual.Murudeshwar Power Corporation is likely to receive Central government clearance for the 18 MW run-of-the-river hydel based power project at river Kali at Dandeli in Uttara Kannada district by July 2008.
The project to be implemented in 6 units of 3 MW each, will entail an investment of Rs.180 crore. Environment Impact Assessment (EIA) study is completed and the company has achieved financial closure for the project.
TCE, Bangalore has prepared the detailed project report for the project. Murudeshwar Power is likely to use its in-house expertise for civil construction and electromechanical works. Currently, the company is awaiting central government clearance and the machinery suppliers is yet to be finalised for the project.