 GAIL India's Dahej-Uran-Dabhol pipeline is expected to be completed by 30 June 2007.

The completion of the pipeline will help Ratnagiri Gas Power (RGPPL) start the Dabhol project. RGPPL expects to run two gas-based units of 740 MW each in full capacity by August 2007. The company has three units of 740 MW each.

Petronet LNG has already committed RGPPL for an immediate supply of roughly 8 mmscmd beginning July 2007. Ratnagiri Gas Power has already revived one unit (block-2) - having two turbines for using gas as feedstock. Revival of the other unit (block-3) is nearing completion. The company is expecting the third unit of RGPPL to be operational by November-December 2007.