The project, estimated to cost Rs 21,396 crore, is facing cost overrun due to a rise in the interest on loans.
At inception, the estimated investment was Rs 12,440 crore. This was revised upwards to Rs 15,870 crore in 2008 and further to Rs 19,535 crore in 2010. The board is yet to approve a new cost for the project. Presently, 93 per cent of the project work has been completed and has a debt of Rs 14,000 crore.
OPaL is a JV between ONGC holding 26 per cent stake, and GSPC and GAIL holding five and 19 per cent, respectively.
The petrochemical complex is likely to be commissioned by June 2015.