Dahej LNG terminal completion by end 2003Illustrative image – not actual.

Petronet LNG has indicated that despite the recent gas find in KG basin, implementation of the Dahej LNG terminal is on schedule with completion likely by December 2003.

 

According to company sources, about 2.5 million tonnes of gas would be made available from the Dahej terminal in the very first year of its operation. On the viability of LNG terminals in context of the recent gas find, the company feels that, its terminals are very much viable, as they are located along the western coast and transportation of gas from Qatar is minimum. Further, gas from the new fields would be available only around 2005-06, while gas from Dahej terminal would be available from end 2003.

 

As of December 2002, about 60 per cent construction work was complete and the first ship is expected to arrive in December 2003.