Illustrative image – not actual.Petronet's LNG terminal at Dahej has achieved physical completion and is expected to receive its first ship by January 2004. The terminal consists of two full containment tanks of 1.6 lakh cubic metres and a 2.5 km long jetty. The first cargo of 1.38 lakh cubic metres of gas will be used for cooling down the process system while three more cargoes will be needed for filling-in the minimum inventory in the two tanks. A consortium led by Ishikawajima Heavy Industries was the EPC contractor the project. Work on the third tank is expected to begin in early 2004.
The company also has plans to double the terminal capacity from current 5 million tpa to 10 million tpa.