Illustrative image – not actual.Daewoo
Power and Asea Brown Boveri (ABB) have planned to withdraw from 1,070 MW Korba
East thermal power project in Madhya Pradesh due to their inability to tie up
funds and the state government’s inability to provide escrow cover for the
project. Financial institutions hesitated to provide funds for the project
following a reduction in the escrow capacity of Madhya Pradesh State
Electricity Board. Further, the Rs.2,000 crore sanctioned by financial
institutions was not disbursed as the project had not achieved financial
closure.
The
project, in which the partners had an equal stake, was estimated to cost $1.4
billion (approx Rs.6,300 crore) . The MoU for the project was signed way back
in October 1994 and most of the clearances were received by 1997. However, the
project has not yet achieved financial closure due to want of funds.
This
withdrawal is the fourth such instance during the last eight to nine months. In
Decemer 1999, Cogentrix of the USA pulled out of the 1,000 MW Mangalore Power
project. In May National Power of the UK decided not to pump in any more funds
into India, which was followed by Electric de France’s exit from the Bhadravati
Power project in Maharashtra.