Dadupur hydel power: Unit I & II to complete by May 2009Illustrative image – not actual.

Work on Unit I and II of 6 MW (4x1500 KW) of Bhoruka Power Corporation's Dadupur hydel scheme in Yamunanagar district of Haryana is expected to be completed by May 2009.

The power project to have four units of 1,500 KW will cost about Rs.50 crore. Of the total investment, around 70 per cent will be funded through bank loans and remaining 30 per cent by internal accruals.

PNR Infrastructure, Chandigarh is the civil & hydro mechanical contractor for the project and till date around 45 per cent of civil and 85 per cent of electromechanical supply works is completed. Work on Unit III and Unit IV of 1,500 KW each is expected to be completed by April 2009.