Illustrative image – not actual.Reliance Energy, on 16 June 2004, signed the State Support Agreement with Uttar Pradesh government for its 3,740 MW gas-based power plant coming up at Dadri in the state.
Uttar Pradesh would get 40 per cent of power generated from this world's largest standalone gas-based power project costing Rs.11,000 crore.
After signing of the agreement, the Reliance group paid Rs.64 crore to the UP government for the purpose of land acquisition.
The project being implemented by a newly-incorporated company, Reliance eGen, would come up in phases. The first phase of 1,200 MW is likely to be commissioned within two years from zero date.
Reliance has reportedly approached banks and financial institutions for financing the project that would have a debt-equity ratio of 9:1.
For all news relating to Dadri power project, click here