India, one of the partners in the plant`s promoter company, Ratnagiri Gas and
Power, is likely to complete two critical pipelines for the purpose - the
Dahej-Uran and the Dabhol-Panvel pipeline - by March 2007. The Dahej-Uran
pipeline will transport regassified LNG from Petronet LNG`s Dahej plant to
Dabhol. The Dabhol power project will get LNG supply for electricity generation.
The two pipelines are part of GAIL`s plans to develop a national gas grid. The
company has lined up investments worth Rs.18,000-20,000 crore for the project.
GAIL is currently implementing four pipelines under the national gas grid. The
Vijaipur-Kota natural gas pipeline for supply in the Rajasthan region and the
Jagoti-Pithampur pipeline for supply of natural gas in Madhya Pradesh are the
other two pipelines besides the Dahej-Uran and Dabhol-Panvel pipelines.
The company is also looking for tie-ups for gas supplies for other pipeline
networks like the Jagdishpur-Haldia pipeline, the proposed Myanmar-Indian
pipeline, the Kochi-Kayamkulam pipeline and the Dadri-Nangal pipeline.
GAIL is in talks with Algerian and Nigerian companies for import of LNG for
Dabhol. Qatar`s Rasgas has also committed to supply 1.2 million tonnes per annum
of LNG.