Illustrative image – not actual.Lenders to the Dabhol Power project are scheduled to meet in Mumbai in June. This is a follow-up to their meeting in London held on 12 May 2004.
The London meeting was rather successful with both sides (foreign lenders and domestic institutions) coming "close to an understanding".
The exposure of foreign lenders is $90 million for Phase I and $272 million for Phase II. Indian institutions led by IDBI have agreed to buy out foreign lenders' debt exposure at a 30 per cent discount.
It may be mentioned that General Electric and Bechtel have acquired bankrupt Enron's 65 per cent stake in Dabhol Power Company through a three-tiered deal. The two US companies now hold a 85 per cent stake in DPC and along with lenders hold the key to reviving the Dabhol project.
The Dabhol power project is lying shut since May 2001. Phase I of 740 MW was fully commissioned and operational at the time of closure, while Phase II of 1444 MW was under construction, with 93 per cent of physical work complete as of May 2001.