Dabhol project revival advanced to 15 MayIllustrative image – not actual.

The Union power ministry has advanced the date of re-commissioning of Phase I of the Dabhol power project to 15 May 2006. The plant will be operation for 2-3 hours per day using naphtha lying stored in the project premises.

Here is the plan of action:

  • Phase I (740 MW) will run for 2-3 hours per day with effect from 15 May 2006 using the 34,000 tonnes of naphtha lying stored in the project premises
  • The plant will operate thus for around three months till gas supplies are tied up
  • Phase II (1444 MW) will be operational from November 2006 onwards
  • The LNG terminal, now 80 per cent complete, will be fully constructed by August 2006