Illustrative image – not actual.The Bombay High Court, on 22 September 2005, has given its go ahead for transfer of assets of the 2,184 MW Dabhol power plant to Ratnagiri Gas & Power Pvt. Ltd, paving the way for restarting the plant before end-2006. Phase I of 740 MW is likely to be re-started by June 2006.
RGPPL would buy the entire assets from the financial institutions for Rs.8,500 crore. The company will also take loan of Rs.7,000 crore from the ICICI-led consortium.
Remaining money would come from the equity of Rs.500 crore each from three partners-NTPC, GAIL and lenders, while another Rs.265 crore would come form Maharashtra Power Development Corporation, which has now been accepted as a direct partner instead of taking preferential share.
Implication: With the court’s approval, RGPPL would not have to approach the Debt Recovery Tribunal for acquiring the assets of Dabhol project that has been shut since 29 May 2001. The court has appointed a receiver for handing over the Dabhol assets to RGPPL.