Dabhol Power Project: Phase I restart put offIllustrative image – not actual.

UK-based investment bank N M Rothschild, the financial adviser appointed by the consortium of domestic lenders to Dabhol Power Company, has recommended against restarting the 750 mw first phase of the project. Tractabel, the technical consultant to the project, had put the cost of reviving the first phase at $15 million.

 

The plan now is to go for a complete solution and not any piecemeal arrangement. Delhi-based Punj Lloyd has been maintaining the plant since it was mothballed in May 2001.

 

The decision to defer the restart of Phase-I suits the needs of foreign lenders that have been demanding a comprehensive solution to the issue. The Overseas Private Investment Corporation (OPIC), which is also a lender to the project, is also keen on a total solution.

 

The exposure of foreign lenders to the project is around $480 million. The team of foreign lenders includes ABN Amro Bank, Credit Suisse First Boston, ANZ Investment Bank, Citibank and OPIC.  Indian lenders have a collective exposure of around Rs 5,850 crore. Of this, Rs 3,350 crore is funded exposure and the rest is in the form of guarantees.

 

General Electric and Bechtel hold a 10 per cent stake each in the beleaguered project, while the Maharashtra State Electricity Board holds 15 per cent in it.

 

Related Stories

 

Tractebel to assist in Dabhol project revival

Revival of Dabhol Phase I pegged at $15 million