Illustrative image – not actual.Ratnagiri Gas & Power Pvt Ltd, the special purpose vehicle that has taken over the defunct 2,184 MW Dabhol power plant, has advanced the date of resumption of the power plant to May-June 2006, from September 2006 earlier announced.
So far, LNG supplies have not been tied up. But Gail (India), the authority concerned with this issue, has stated that negotiations with 4-5 suppliers have begun.
The plant is likely to begin operations with 33,000 kilolitres of imported naphtha that is lying in one of the tanks at the under-construction LNG terminal.
There is some uncertainty over the power tariff, which is likely to exceed Rs.2.50 per unit (kwh) in view of the rising prices of LNG.
RGPPL has made a total investment of Rs.10,303 crore including Rs.1,765 crore as equity in the new plant. This value is two-thirds the original value of the plant. The debt has been financed by Indian banks led by IDBI. The Bombay High Court, in September 2005, allowed the transfer of assets from Dabhol Power Co to RGPPL, for a total consideration of Rs.8,485 crore.
The shareholders in RGPPL are NTPC (28.33 per cent equity stake), GAIL (28.33 per cent), MSEB Holding Co (15 per cent) and Indian lending institutions (28.33 per cent). Domestic lending institutions include IDBI, State Bank of India, Bank of India, ICICI Bank and Canara Bank.
Also See:
Dabhol power project revival: Court approves asset transfer (24-Sep-05)