Dabhol LNG terminal to be operational by April 2010Illustrative image – not actual.

Ratnagiri Gas and Power Pvt Ltd's (RGPPL) 5 million tpa LNG terminal at Dabhol in Maharashtra is likely to be operationalised by April 2010.

The Re 3,000 crore proposed terminal has reportedly achieved mechanical completion and RGPPL is likely to commission the terminal after completion of the dredging works.

Commissioning of the terminal has been delayed due to pending dredging of the channel to allow LNG ships enter the port. There has been excessive silt accumulation due to bad weather, which needs to be dredged. The dredging is likely to take about a month from the award of contracts.

On completion, the terminal is likely to supply 2.1 million tonne re-gassified LNG for captive use and 2.9 million tonne for merchant sale. Initially, the terminal is expected to operate at around 40 per cent capacity. To achieve full capacity, the terminal will need a breakwater to run through the year. The breakwater is likely to cost Rs 1,500-2,000 crore and is expected to take three years for completion from the award of contracts.

Also See:

RNRL in fray to hire LNG terminal near Dabhol plant (17-Jun-09)

Related Links:
Project profile

← All latest storiesBack to top →