Dabhol LNG terminal to be commissioned by end-MarchIllustrative image – not actual.

Ratnagiri Gas and Power Private's (RGPPL) Rs.2,700 crore Dabhol LNG terminal is likely to be commissioned by end-March 2009.

Initially, the plant which was meant to feed the adjoining power plant but would now supply to other domestic companies. However, the gas from the terminal will not be used to run the power plant, which had been allocated gas from the Reliance Industries' block in the Krishna-Godavari basin. This supply is likely to start in the next few weeks.

The terminal has an LNG re-gasification capacity of five million tpa. It will, however, be fully operational only after the completion of the breakwater facilities in 2011. On completion, RGPPL will invite EoIs from companies to decide the price for providing the regasification facility.

At present, India has two LNG terminals - Dahej and Hazira terminal, both of them are in Gujarat.