CWC nod for revised estimate cost of Polavaram projectIllustrative image – not actual.

The technical advisory committee of the Central Water Commission (CWC) has cleared the revised cost estimate of Rs 55,548 crore of the mega Polavaram project on the Godavari in Andhra Pradesh.

The revised cost estimate will now have to be cleared by the Union Finance Ministry. Following this it will go for the Cabinet approval.

The mega irrigation project was mentioned as a national project in the Andhra Pradesh Re-organisation Act, 2014.

The cost of the project was pegged at Rs 16,010.45 crore at 2010-11 rates and the State government had submitted a revised cost estimate, taking into account cost escalation.

Moreover, the state government is seeking reimbursement by the Centre of Rs 3,866.79 crore already spent on the project, but pending clearance of the revised cost estimate and revised DPR the Centre is unable to release the funds.

Of the revised cost, an amount of nearly Rs 33,000 crore will to towards relief and rehabilitation (R&R) package and the rest on the dam and canals.

Around 65 percent of the work on the dam has been completed and it is expected to be completed by the year-end, and to release water by gravitational flow for the coming kharif season itself even before the completion of the project. So far, Rs 15,585 crores has been spent on the project.

 