Illustrative image – not actual.The Central Water Commission (CWC) has returned Karnataka’s revised detailed project report (DPR) for the Mekedatu project, stating that the proposal does not conform to the Cauvery Water Disputes Tribunal (CWDT) award and the Supreme Court’s 2018 judgment.
The DPR was returned to Karnataka on June 29 for suitable modifications after the state proposed changes that expanded the volume of water earmarked for consumptive use by 2.2 thousand million cubic feet (tmcft). Karnataka had initially proposed the Mekedatu project in 2018 as a balancing reservoir aimed at diverting around 23.75 tmcft of Cauvery water, including 4.75 tmcft for drinking water supply to Bengaluru and surrounding areas. The CWC had provided in-principle approval for DPR preparation in November 2018 based on the original proposal. However, the revised DPR submitted in April introduced additional components, including the Shivanasamudra Run-of-River Power Project, and increased consumptive use requirements from 4.75 tmcft to 6.95 tmcft.
The CWC noted that these changes were not part of the original DPR submitted in 2019 and questioned the justification for a reservoir with a live storage capacity of 59.46 tmcft.