Current Status of Orders awarded in June 2010 (PT Exclusive)Illustrative image – not actual.

ProjectsToday exclusively brings to you, the current status of various projects awarded to India based companies in the month of June 2010.

They are:

  • Work on the four/six laning of NH-17 section between Maharashtra-Goa border to Panaji-Goa-Karnataka border is under planning stage. The Rs 3,100-crore contract was awarded to IVRCL Infrastructures & Projects.
     
  • Jaihind Projects' slope correction & lining of fifth phase of tailing dam project at Rampura Agucha Mines, Bhilwara district of Rajasthan is underway with completion in May 2011. The contract for steel pipeline network construction for Anjar, Adipur and Gandhidham city gas distribution project is underway, slated to be completed by January 2010. Also, equipment erection, station piping, mechanical, civil, electrical & instrumentation work for the Sanganer Rehabilitation project in Jaipur is under execution. It is to be completed by December 2010.
     
  • Punj Lloyd is constructing a technical institute at Jais in Rae Bareli, Uttar Pradesh, which is likely to become functional by August 2012.
     
  • Ashoka Buildcon is currently upgrading the Sambalpur-Baragarh (Orissa) and Belgaum-Dharwad (Karnataka) road projects. Both the projects are likely to be completed by December 2011.
     
  • Nagarjuna Construction has begun construction of hospital buildings at Mumbai. The company is developing Green Wood Apartments at Gomti Nagar in Lucknow and has also commenced construction of various buildings at a radial tyre manufacturing plant at Perambalur, Tamil Nadu. All three projects are slated to be completed in 2012.
     
  • PBA Infrastructure was given an order by MIDC for the construction of WMM road with asphalt treatment including central road divider and allied work in IT Park-II (Phase-I) in Nagpur Industrial Area. The work is underway, with completion scheduled for 2012.
     
  • Ahluwalia Contracts had bagged two real estate projects from Utkal Builders. Work on the residential project at Pahal and Utkal Royal Residency at Gautambagar in Orissa is under execution. Meanwhile, its Utkal Kanika Galleria at Gautambagar in Bhubaneshwar is still under planning stage. Work is likely to commence in December 2010.
     
  • Madhya Pradesh State Tourism Development Corporation had given a contract to Sayaji Hotels for building a 4/5 star hotel project at Kotra Sultanabad, in Bhopal district. Work is slated to begin in 2011.
     
  • Work on the WMM road including central road and allied work at IT Park (Phase I) in Nagpur Industrial Area is underway. PBA Infrastructure is carrying out the work which is to be completed by September 2010.

prjexcl